Akela Ground Engineering has completed the design and installation of a full precast foundation system to support eight Battery Energy Storage System (BESS) units and two Power Conversion System (PCS) units for Emtec in Sandwich, Kent.
Delivered in less than eight weeks, the project demonstrates the capability of modern methods of construction (MMC) to support the rollout of critical lowโcarbon energy infrastructure.
To address highly variable ground conditions, including soft superficial deposits, granular bearing strata and surcharge loading from stored biomass, Akela designed a tailored foundation solution comprising 200 ร 200 mm driven precast concrete piles installed to depths of up to 15 metres. These were integrated with the companyโs innovative ABeam precast ground beam system.
On site, more than 800 linear metres of driven precast piling were installed in under five days, followed by 220 linear metres of ABeam ground beams within a further two days.
ABeam features an innovative mechanical pinned joint that allows prefabricated beams to be installed in hours rather than days. The system eliminates the need for inโsitu concrete, pile caps, tie bars or followโon trades, enabling a fully controlled, weatherโindependent installation process.
Manufactured at Akelaโs stateโofโtheโart precast facility near Glasgow, using renewable groundโsource heating to reduce carbon impact, ABeam ensures consistent quality while supporting more sustainable construction practices.
Offsite manufacture significantly reduced site congestion and removed weather dependency, a key advantage given the project commenced in November.
Akela also deployed its latest JX piling fleet, reducing working platform requirements and minimising excavation volumes to deliver both cost and programme efficiencies.
Will Payne, managing director of Akela Ground Engineering, said: โABeam represents a step change in how foundation systems can be delivered. By removing the need for inโsitu concrete, followโon trades and weatherโdependent sequencing, weโre giving clients a faster, cleaner and more predictable way to build.
โThis project is a great example of the system in action – delivering speed, quality and longโterm performance while supporting the rollout of essential renewable energy infrastructure.โ
The completed foundation system provides a robust, efficient and sustainable platform for the BESS and PCS units, supporting the UKโs transition to a more resilient, lowโcarbon energy grid and demonstrating the realโworld impact of combining offsite manufacture with modern piling technology.